Project Summary
Backyard Transformation

Comprehensive backyard transformation including a natural basalt patio with seat walls, flagstone pathway connecting front and rear yards, perennial garden beds with drip irrigation, and landscape lighting throughout. Design prioritizes low-water plantings suited to Central Oregon's high desert climate.

Estimate Date
April 8, 2026
Valid Until
May 8, 2026
Est. Timeline
4 - 5 Weeks

Scope of Work
  1. Site Preparation. Clear existing vegetation, grade the rear yard for proper drainage, and establish access paths for materials delivery.
  2. Patio and Seat Walls. Install a 480 sq ft natural basalt patio with a 24 linear ft seat wall featuring integrated drainage, set on a compacted gravel base.
  3. Pathway. Build a flagstone pathway from the front entry to the rear patio with decomposed granite borders and landscape fabric underlayment.
  4. Perennial Garden. Install a 320 sq ft perennial garden bed with drought-tolerant species selected for USDA Zone 6b, including soil amendments and cedar mulch.
  5. Irrigation and Lighting. Install a 4-zone drip irrigation system with smart controller and 8 low-voltage LED landscape lights along pathways and patio.
  6. Final Grading and Cleanup. Final grade all disturbed areas, seed bare soil, remove all debris, and complete a detailed walkthrough.

Detailed Line Items
# Description Qty Unit Unit Price Amount
Site Preparation
1 Site clearing and grading 1 LS $2,800.00 $2,800.00
Subtotal $2,800.00
Hardscape
2 Natural basalt patio, dry-laid on gravel base 480 SF $18.50 $8,880.00
3 Basalt seat wall with cap stones 24 LF $145.00 $3,480.00
4 Flagstone pathway, natural edge 1 LS $3,200.00 $3,200.00
5 Decomposed granite border, compacted 1 LS $1,100.00 $1,100.00
Subtotal $16,660.00
Planting and Softscape
6 Perennial garden bed, plants and soil prep 320 SF $12.75 $4,080.00
7 Cedar mulch, 3" depth 1 LS $680.00 $680.00
Subtotal $4,760.00
Irrigation and Lighting
8 4-zone drip irrigation system w/ smart controller 1 LS $2,400.00 $2,400.00
9 LED landscape lighting, 8 fixtures + transformer 8 EA $285.00 $2,280.00
Subtotal $4,680.00
Cleanup and Completion
10 Final grading, seeding and debris removal 1 LS $1,200.00 $1,200.00
Subtotal $1,200.00
Design and Planning
11 Design, plans and project management 1 LS $1,800.00 $1,800.00
Subtotal $1,800.00
Subtotal $31,900.00
Tax Included
Total $31,900.00

Project Timeline

Payment Terms
Deposit (40%)
$12,760.00
Due upon acceptance
Midpoint (30%)
$9,570.00
At completion of hardscape
Final (30%)
$9,570.00
Upon final walkthrough
Accepted Methods
Check, bank transfer, credit card

Payments are due within 7 days of invoice.


Terms and Conditions
  1. This estimate is valid for 30 days from the date issued.
  2. Work will be scheduled upon receipt of signed acceptance and deposit payment.
  3. Any changes to the scope of work require a written change order signed by both parties.
  4. Unforeseen site conditions (rock, buried utilities, or similar) may result in additional charges, communicated in advance.
  5. All work will be performed in accordance with local building code requirements.
  6. Site cleanup and debris removal are included in the project scope.
  7. Workmanship is warranted for one year from project completion. Plants are guaranteed for one growing season, with replacement provided for any that fail to establish.
Acceptance and Authorization

By signing below, you accept this estimate and authorize Stonebrook Landscape Design to begin work as described above. This agreement is subject to the terms and conditions stated in this document.

Client
Signature
Printed Name
Date
Contractor
Signature
Printed Name
Date